Make to Order vs Make to Stock: How to Choose (Decoupling Point, Hybrid Strategy and Cost Guide)

Make to order vs make to stock: how to choose? We explain the decoupling point, decision criteria, hybrid ATO strategy and cost with a worked example.

Contents 16 sections
  1. What Are Make to Order and Make to Stock?
  2. How Do the Four Strategies Compare?
  3. What Is the Decoupling Point and Where Should It Go?
  4. Which Criteria Should Drive the Choice?
  5. How Does Delivery Time Build Up?
  6. How Do You Work Out the Economics of MTS and MTO?
  7. How Do You Build a Hybrid for a 12-Variant Product Family?
  8. How Do You Reduce Variant Explosion?
  9. What Are the Typical Problems of MTO and MTS?
  10. When Should the Strategy Change?
  11. Which Measures Should You Track?
  12. How Is It Set Up in an ERP?
  13. How Do You Calculate the Payback?
  14. Six Steps to Choose a Strategy
  15. Production and Stock Processes with İnovabil
  16. Frequently Asked Questions

In the same factory, one product waits on a shelf while another is never touched until an order arrives. In most businesses that choice is made out of habit, yet it directly changes the capital tied up in stock, the delivery time and the sales you lose. Choosing between make to order (MTO) and make to stock (MTS) answers one question for each product: do we keep the customer waiting, or do we carry the inventory?

This guide covers the four production strategies, the decoupling point, the decision criteria, a cost calculation for a 12-variant product family, a hybrid set-up, how to change strategy over time and how it is configured in an ERP. MRP net requirements and capacity are covered in separate articles; here we focus on the choice itself. All figures are illustrative.

Key takeawayMTS and MTO are not alternatives to each other but two ends of a scale used together inside one product family. If the time a customer will wait is shorter than the total production time, you need stock; if it is longer, you can build to order. The decision is made product by product: a few fast-selling variants go to stock, while rare and highly varied ones are served from common-component stock and built on order.

What Are Make to Order and Make to Stock?

MTS produces to a forecast and keeps finished goods in stock, so the product is ready when the customer arrives. MTO starts production only when a customer order is received and holds no finished goods. Two strategies sit in between: ATO (assemble to order) keeps semi-finished parts or modules in stock and assembles them on order, and ETO (engineer to order) designs the product to the order.

In short, a strategy answers "which stage of production waits for an order?" Work done before the order rests on a forecast and creates stock; work done after the order shows up as customer waiting time.

How Do the Four Strategies Compare?

The four strategies differ on five measures: the delivery time the customer sees, stock, flexibility, resilience to demand uncertainty and capacity utilisation.

MeasureMTSATOMTOETO
Delivery timeShortestShortLongLongest
StockHigh finished-goods stockComponent and semi-finished stockRaw material onlyAlmost none
FlexibilityLow; ready-made optionsMedium; combinations are chosenHigh; built to the customerVery high; the design changes
Demand uncertaintyHarmful; stock ages or runs outMedium; pooledResilient; orders set the demandResilient
Capacity utilisationEven; production is levelledUneven at assemblyUneven; jams at the peakVery uneven
Typical productStandard, high volumeOptional, modularCustom size, low volumeProject product

What Is the Decoupling Point and Where Should It Go?

The decoupling point is the place in the production chain where forecast-driven work ends and order-driven work begins. Everything to its left creates stock; everything to its right turns into customer waiting time.

Decoupling pointStrategyHeld in stockWhat the customer waits for
At finished goodsMTSFinished productShipping only
At semi-finishedATOCommon components, semi-finished partsFinal assembly and shipping
At raw materialMTORaw materialSourcing, production and shipping
Before designETONothingThe whole chain, design included

Moving the point to the right cuts stock and increases variety; moving it to the left speeds up delivery but enlarges stock and forecast risk. The aim is to find the right-most point that still fills the time the customer is willing to wait.

Which Criteria Should Drive the Choice?

There are six criteria, and each pushes a product toward one end.

CriterionPushes toward MTSPushes toward MTO or ATO
Forecast errorLow; steady demandHigh; volatile demand
Customer waiting timeShorter than production timeLonger than production time
Product varietyFew variantsMany variants, combinations
Shelf life and fashionLong-lived, stable productShort life, frequent model changes
Unit valueLow; stock is cheapHigh; stock is expensive
Weekly demand volumeHigh and steadyLow and irregular

Turning the criteria into numbers simplifies the decision. Our example rule (thresholds are illustrative): a variant with weekly demand of at least 40 units, a forecast error no higher than 30% and a customer waiting time shorter than the production time is an MTS candidate. A variant with unknown, new or customer-specific demand goes to MTO, and one with common components goes to ATO. ABC analysis shows which products carry the weight, and the demand forecasting guide covers measuring forecast error.

We recommend reading: How to do demand forecasting: method, error measures and safety stock

How Does Delivery Time Build Up?

The delivery time a customer sees is the sum of four parts: order processing, material sourcing, production and shipping. Which parts can be finished before the order arrives determines the strategy.

PartMTSATOMTO
Order processing1 day1 day1 day
Material sourcing0 (in stock)0 (components in stock)4 days
Production0 (ready)1 day (final assembly)3 days
Shipping2 days2 days2 days
What the customer waits3 working days4 working days10 working days

Cumulative lead time from scratch is 1 + 4 + 3 + 2 = 10 working days. If the customer will wait 7 working days, MTO is 3 days late while ATO leaves a 3-day margin. The answer is not to put the whole product into stock but to stock just enough of it to bring the time from 10 days down to 4.

How Do You Work Out the Economics of MTS and MTO?

Two costs face each other: the holding and obsolescence cost of MTS, and the sales that slip away under MTO because the customer is kept waiting. The threshold loss rate for one variant is:

Threshold rate = (weeks of cover × unit cost × (holding rate + obsolescence rate)) ÷ (weeks per year × unit margin)

With illustrative values: unit cost ₺400, selling price ₺600 (margin ₺200), annual holding 25%, obsolescence 6% on a rare variant, 6 weeks of cover and a 48-week year (4 weeks × 12 months). Numerator: 6 × 400 × 0.31 = ₺744, the yearly stock cost of one unit of weekly demand. Denominator: 48 × 200 = ₺9,600. Threshold: 744 ÷ 9,600 = 7.75%. If more than 7.75% of orders walk away because of the wait, holding stock is cheaper; if fewer do, building to order is cheaper. When 20% leave once the promise passes 7 days, MTS wins.

TipLost sales are hard to estimate. Ask the sales team how many customers went elsewhere on quotes promising more than 7 days, and count them from the last three months of quotes.

How Do You Build a Hybrid for a 12-Variant Product Family?

The example family has 12 variants from 3 sizes and 4 colours, total demand of 1,200 units a month (300 a week), cost ₺400 and price ₺600. The three best sellers have weekly demand of 60, 50 and 40 (total 150, half of demand); the other nine share 150 units, from 27.5 down to 5.

If everything is MTS, the top three need 2 weeks of cover and the rare ones 6 weeks because their forecast error is higher: 150 × 2 + 150 × 6 = 1,200 units, ₺480,000 of stock. In the hybrid, three variants stay MTS (300 units, ₺120,000) and nine move to ATO: the body is held semi-finished by size, and colour and final assembly happen on order. The semi-finished cost is ₺300; because demand is pooled, cover falls to 3 weeks: 150 × 3 = 450 unit equivalents, ₺135,000. Only part of the pooling effect is counted, which is a cautious assumption.

The annual cost of the nine rare variants under three strategies is below (raw-material stock is common to all three and left out; under MTS a stock-out is assumed to make the customer wait rather than lose the sale).

StrategyCapital tied upHolding and obsolescenceLost salesAnnual totalDelivery
MTS₺360,000₺90,000 + ₺21,600None₺111,6003 days
MTONoneNone20% = ₺288,000₺288,00010 days
ATO₺135,000₺33,750 + ₺1,3502% = ₺28,800₺63,9004 days

The working: for MTS, 900 units × ₺400 = ₺360,000; holding at 25% = ₺90,000; obsolescence 900 × 6% = 54 units = ₺21,600. For MTO, 20% of the 600 monthly units is 120; 120 × ₺200 × 12 = ₺288,000. For ATO, holding is 135,000 × 25% = ₺33,750, semi-finished obsolescence at 1% is ₺1,350, and 2% lost is 12 units; 12 × 200 × 12 = ₺28,800.

Annual cost of the nine rare variants: MTS 111,600 lira, MTO 288,000 lira, ATO 63,900 lira
For rare variants, ATO gives the lowest annual cost.

Overall comparison: all MTS costs 480,000 × 25% + 21,600 = ₺141,600 a year. In the hybrid, holding the three MTS variants is 120,000 × 25% = ₺30,000, plus the ATO line of ₺63,900, giving ₺93,900. The difference is ₺47,700 a year. Stock also falls from ₺480,000 to ₺255,000 (₺225,000 less, 46.9%); days of stock (365 ÷ turnover) with annual cost of sales of 5,760,000 fall from 30.4 days to 16.2, and turnover rises from 12.0 to 22.6.

Sensitivity: if lost sales under ATO are 6% instead of 2%, the hybrid costs ₺151,500 and becomes dearer than all MTS. The break-even loss is 31.9 units ÷ 600 = 5.3%. The hybrid wins only if the delivery promise is actually kept.

How Do You Reduce Variant Explosion?

As options multiply, the number of finished products multiplies while the number of common components only adds up. 4 bodies, 3 finishes and 5 accessory packs make 4 × 3 × 5 = 60 different products; with a modular design only 4 + 3 + 5 = 12 components are stocked. Stock items fall to 12 ÷ 60 = 20% (80% fewer). Each finished product needs its own forecast, whereas each component pools the demand of many products, so forecast error shrinks by itself.

How valid combinations and prices are managed by rules is covered in our product configurator article.

We recommend reading: What is a product configurator (CPQ)? Rules, pricing and bill of materials

What Are the Typical Problems of MTO and MTS?

For MTO the problem is capacity swings. If average weekly orders are 150 units with a swing of ±40%, weeks range from 90 to 210. With capacity of 160 units, the peak week builds up 50 units, which is an extra delay of 50 ÷ 160 × 5 ≈ 1.6 working days. Framework agreements and advance orders that make 40% of the load (60 units) known in advance cut the swing to ±40% of the remaining 90, which is ±36; the peak becomes 186 units and the capacity needed falls from 210 by 24 units (11.4%).

For MTS the problem is forecast bias. If a rare variant is forecast at 30 a week and actual is 22.5, bias is 7.5 ÷ 22.5 = +33.3%. In 12 weeks 90 excess units build up: cover rises from 6 weeks (135 units) to 10 weeks (225 units), tying up an extra 90 × 400 = ₺36,000. How safety stock is set is covered in a separate article.

When Should the Strategy Change?

Strategy moves with the product life cycle. With a new product demand is unknown, so you start with MTO or small batches. Once demand settles and forecast error drops, you move to MTS. As the product ages you move back.

  • MTO to MTS: weekly demand above 40 units for 8 weeks in a row and forecast error below 30% (illustrative thresholds).
  • MTS to ATO or MTO: demand stays below 25 units for two consecutive quarters, or the share of stock older than 180 days grows.
  • During the switch: run down existing stock, and open the new order type only once stock is gone.

The thresholds differ in the two directions (40 and 25) on purpose; this prevents the cost of flipping back and forth at the boundary.

Which Measures Should You Track?

Four measures are enough: days of stock, on-time delivery, lost sales and the share of obsolete stock. Rising days of stock point to bias under MTS. Falling on-time delivery (delivery within the promised time) points to a capacity or component problem under MTO or ATO. Lost sales are the numerical counterpart of the waiting cost. The share of obsolete stock is stock older than 180 days as a share of the total; in the example rare stock it is 54 ÷ 900 = 6.0%.

Track the measures separately by strategy; a blended average can hide an MTS problem behind a good MTO result.

How Is It Set Up in an ERP?

In an ERP the strategy is recorded in a supply strategy field on the item record (MTS, ATO, MTO, ETO). Planning behaves according to that field: for MTS items a replenishment order tied to the forecast and the stock target is raised, for MTO items a work order tied to the customer order, and for ATO items a stock order for the semi-finished part plus an assembly order tied to the customer order. The bill of materials carries a stock item at the decoupling point; if the semi-finished part is not coded separately, ATO cannot be set up.

How net requirements are calculated through the bill of materials is covered in our production planning guide, and how the bottleneck is found in our capacity planning article. Opening different work orders by order type and keeping the strategy per product is core work for ERP software.

We recommend reading: How to do production planning: net requirements, capacity and schedule
We recommend reading: What is supply chain management? Bullwhip, stock and cash cycle

How Do You Calculate the Payback?

The investment, for the item record field, work order types, semi-finished coding and training, is an illustrative ₺90,000. The annual net gain is the difference between the hybrid and all MTS: ₺47,700, or ₺3,975 a month. Payback is 90,000 ÷ 3,975 ≈ 22.6 months. In addition, ₺225,000 of cash is released once; this is not profit but capital freed, and is recorded separately.

If lost sales rise to 6%, the difference turns negative (₺151,500 against ₺141,600) and there is no payback. So before moving to ATO, test on one pilot variant that the delivery promise is kept.

Six Steps to Choose a Strategy

The sequence below sets the strategy product by product, in a measurable way.

Six steps to choose between MTO and MTS: variant list, demand and forecast error, customer waiting time, decoupling point, hybrid cost, pilot and measurement
The six steps of choosing a strategy.
  1. List the variants: write down weekly demand and forecast error.
  2. Ask about waiting time: set the time the customer will accept with the sales team.
  3. Split the time: fill in the four-part delivery table.
  4. Choose the point: find the right-most point that meets the time.
  5. Calculate the cost: work out the annual total and the sensitivity for three strategies.
  6. Pilot and measure: test on one variant and track with four measures.
We recommend reading: How to Estimate Costs for Custom Product Quotes: Estimating Methods, Risk Allowance and Quote Pricing Guide

Production and Stock Processes with İnovabil

At İnovabil our focus is software built from scratch for your company: custom software, ERP, CRM, e-commerce, web, mobile and integration. We suggest putting in writing, during requirements analysis, how the supply strategy will show up in the item record, the work order type and planning; the decision is made product by product, using your data.

We have built warehouse management for Sleepy, logistics and shipment planning with wholesale order management for Karyak, shipment planning for Bofigo, CRM, purchasing and mobile for Avcılar İnşaat, and a purchasing system for İZBAN. If you briefly describe your product family and your delivery-time expectation, we can examine the decoupling point together as part of the process.

We recommend reading: Our software development process: step by step from analysis to launch

Frequently Asked Questions

What is the difference between MTO and MTS?

MTS produces to a forecast and holds stock, while MTO produces only when an order arrives. MTS gives fast delivery but carries stock and forecast risk; MTO carries no stock but keeps the customer waiting.

What is a decoupling point?

It is the place in the production chain where forecast-driven work ends and order-driven work begins. Its left side is stock and its right side is customer waiting time; at finished goods it is MTS, at semi-finished it is ATO, at raw material it is MTO.

Which products are made to stock?

Standard, high-volume products with steady demand, low forecast error, long shelf life and low unit value. Stock is also unavoidable when the time the customer will wait is shorter than the production time.

When does ATO make sense?

When many variants are built from a few common components and final assembly is short. In the example 60 finished products reduce to 12 components, and delivery falls from 10 days to 4.

When should the strategy be changed?

As the product life cycle moves on: MTO for a new product, MTS once demand settles, and back to ATO or MTO when demand falls. Write the switching thresholds down and keep them different in the two directions.