Your store room holds 3,500 spare parts, and most of them move no more than three times a year. Yet a single missing drive card can stop a production line for days. Spare parts inventory management is the discipline of covering that rare and irregular demand with a stock level that matches how critical each part is. It applies both to the maintenance of your own machine park and to the after-sales service of the products you sell.
This guide shows how to classify demand patterns, forecast intermittent demand, set stock levels with probabilities, decide whether one expensive part should sit on the shelf, and handle pooling, repair and obsolescence, with a payback calculation at the end. All figures are representative; they are not data from a particular company or industry.
How Is Spare Parts Inventory Different From Normal Stock?
Stock held for sale sees steady, forecastable demand. A spare part is rarely needed, but when it is needed it is needed urgently. That is why familiar measures such as turnover do not guide decisions on their own.
| Topic | Stock for sale | Spare parts stock |
|---|---|---|
| Number of items | Relatively few, fast moving | Many (3,500 in our example); most move 0-3 times a year |
| Demand | Continuous, seasonal | Sparse, irregular, sometimes arriving in lumps |
| Cost of a stock-out | Lost sale | Downtime hours, often far above the part price |
| Lead time | Short, repeating | Long, sometimes months |
| Main risk | Excess stock | Obsolescence and end of model |
| Decision criterion | Cost and service level | Criticality and downtime cost |
The basic logic of stock for sale is covered in our inventory tracking guide. To see the spare parts angle from the maintenance side, read our maintenance management software article; for parts of the products you sell, our warranty and after-sales service article is the place to start.
How Do You Classify the Demand Pattern?
Every part's demand is summarised with two numbers. ADI (average demand interval) = number of periods ÷ number of periods with demand. CV² is the squared coefficient of variation of the demand sizes in the periods that had demand, (standard deviation ÷ mean)²; it shows how much the size swings. The commonly used cut-offs in the literature are 1.32 for ADI and 0.49 for CV².
ADI below 1.32 with CV² below 0.49 is smooth demand. Small ADI with large CV² is erratic. Large ADI with small CV² is intermittent. Both large is lumpy. Eight parts over 24 representative months:
| Part | Months with demand | ADI | CV² | Total units | Class |
|---|---|---|---|---|---|
| Filter | 24 | 1.00 | 0.03 | 65 | Smooth |
| Bearing | 19 | 1.26 | 0.87 | 53 | Erratic |
| Shaft seal | 6 | 4.00 | 0.00 | 12 | Intermittent |
| Drive card | 4 | 6.00 | 0.12 | 5 | Intermittent |
| Motor | 3 | 8.00 | 0.78 | 8 | Lumpy |
| Sensor | 16 | 1.50 | 0.11 | 24 | Intermittent |
| Coupling | 4 | 6.00 | 0.42 | 11 | Intermittent |
| Gearbox | 2 | 12.00 | 0.00 | 2 | Intermittent |
The class decides the method: classic forecasting works for smooth parts and fails for intermittent and lumpy ones. We cover the classic methods in our demand forecasting guide; the sections below deal only with the intermittent case.
How Do You Forecast Intermittent Demand?
Demand size and the interval between demands are smoothed separately and then divided. This idea is known as the Croston approach; here we show its logic through an example rather than the formula.
The shaft seal was requested 6 times in 24 months, about 2 units each time, roughly once every 4 months. Expected monthly demand = 2 ÷ 4 = 0.5 units. A three-month moving average on this part shows 2 ÷ 3 = 0.67 for the three months after a request and 0 in the fourth, so the forecast swings around a rhythm that never changed. Showing zero is also misleading: you cannot leave the part out of stock because "nothing is expected next month". A method that tracks size and interval separately stays at 0.5.
How Do You Set the Stock Level With Probability?
A bell curve (normal distribution) is a poor model for spare parts demand: demand is a few units at most, cannot go below zero and is zero in most periods. The Poisson distribution suits rare events and has a single parameter, the expected demand during the lead time, λ. The safety stock formula is explained in our safety stock and reorder point guide; here we build the probability table that replaces it.
For the shaft seal, λ = 0.5 units a month × 4 months of lead time = 2 units. With a stock position of s units, the probability that lead-time demand does not exceed s is P(demand ≤ s):
| Stock s (units) | P(demand ≤ s) | Expected unmet units |
|---|---|---|
| 2 | 67.7% | 0.54 |
| 3 | 85.7% | 0.22 |
| 4 | 94.7% | 0.08 |
| 5 | 98.3% | 0.02 |
| 6 | 99.5% | 0.01 |
For a 95% target, s = 4 is not enough (94.7%, just under); you need s = 5. The calculation assumes demand arrives unit by unit and independently; if it arrives in lots of 2, the real need is higher. To see how it differs from a normal-distribution calculation, compare three values of λ:
| λ | Normal, 95% | Poisson, 95% | Normal, 99% | Poisson, 99% |
|---|---|---|---|---|
| 0.3 | 2 | 1 | 2 | 2 |
| 1 | 3 | 3 | 4 | 4 |
| 2 | 5 | 5 | 6 | 6 |
The normal approximation (λ + z × √λ, rounded up; z = 1.645 and 2.326 are the usual values) gives the same answer for λ of 1 or more and one unit extra for very rare parts. The real problem is the lumpy part (the motor: 8 units over three requests, one of them 6): both models fall short there. For such parts, look at actual lead-time totals from history and let criticality drive the decision.
How Do You Choose the Service Level by Criticality?
Not every part gets the same target. Criticality combines three things: the effect of a failure (does the line stop, is there a safety risk), whether a backup exists and the lead time. Example targets and what they mean for λ = 2 (part price ₺8,000, representative):
| Class | Target | Stock s | Actual probability | Stock value |
|---|---|---|---|---|
| A, critical | 99% | 6 | 99.5% | ₺48,000 |
| B, important | 95% | 5 | 98.3% | ₺40,000 |
| C, auxiliary | 85% | 3 | 85.7% | ₺24,000 |
Going from 5 to 6 adds ₺8,000 and lifts the probability by only 1.2 points; on a part with expensive downtime that extra cost is worth it, on cheap downtime it is waste. Classification by value is covered in our ABC analysis article; here the criterion is not value but downtime impact.
Should a Single Part Be Kept in Stock?
For rare but expensive parts, the decision comes down to one comparison: is the yearly expected downtime loss avoided by holding the part larger than the yearly carrying cost of the stock? Yearly gain = expected failures per year × (wait without stock − swap time) × downtime cost per hour. Carrying cost = part price × 25% (capital, storage, obsolescence; representative). Swap time is taken as 4 hours; the calculation assumes a replacement is ordered once the stocked part is used and that a second failure within the lead time can be ignored.
| Part | Price | Failures a year | Wait without stock | Downtime per hour | Yearly gain | Carrying (25%) | Decision |
|---|---|---|---|---|---|---|---|
| Drive card | ₺42,000 | 0.25 | 240 h | ₺3,000 | ₺177,000 | ₺10,500 | Hold |
| Coupling | ₺6,500 | 0.40 | 120 h | ₺1,500 | ₺69,600 | ₺1,625 | Hold |
| Large gearbox | ₺180,000 | 0.05 | 360 h | ₺3,000 | ₺53,400 | ₺45,000 | Borderline; share |
| Sensor | ₺2,800 | 2.00 | 24 h | ₺1,000 | ₺40,000 | ₺700 | Hold |
| Converter | ₺85,000 | 0.02 | 24 h | ₺1,500 | ₺600 | ₺21,250 | Do not hold; fast supply |
The converter is the interesting case: it looks expensive and critical, but if it fails very rarely and the supplier delivers within 24 hours, tying up capital gains nothing. The opposite case is the insurance spare: it may sit unused for years, but it is held because on the day it is needed the downtime costs more than the part. Such parts must not be deleted from the dead-stock report; flag them as critical.
Can Pooling, Fast Supply or Consignment Replace Stock?
Partly. If three sites use the same part, shared stock gives a risk-pooling effect. With λ = 0.5 per site over the lead time and a 95% target, each site holds s = 2 (98.6%): 6 units in total. Pool the three sites and λ becomes 1.5; s = 3 is not enough (93.4%), s = 4 is (98.1%). The same service level is achieved with 4 units instead of 6. If the part is the ₺42,000 drive card, the two-unit difference is ₺84,000 of stock and ₺21,000 a year in carrying cost. The condition is that transfers between sites are quick.
A fast-supply agreement shortens the lead time, which lowers λ and the stock needed. Consignment stock held at the supplier shifts the capital to the supplier; see our consignment inventory article and, for the model where the supplier manages your stock, our VMI article. The transfer and visibility side of multi-site stock is covered in a separate guide.
Is Repairing a Part Cheaper Than Buying a New One?
Often, yes. Say a new part costs ₺48,000, a repair costs ₺16,000 and the repair succeeds 80% of the time. Since the failed 20% need a new part, the expected cost is 16,000 + 0.2 × 48,000 = ₺25,600, which is 46.7% below the new price. In this loop the repair cycle (repair, shipping, test) replaces the supplier lead time. With 6 demands a year and a 2-month cycle: λ = 6 × 2 ÷ 12 = 1 and for 95% s = 3 (98.1%; at s = 2 it is 92.0%). Buying new with a 4-month lead time gives λ = 2 and s = 5. The rotating pool drops from 5 to 3.
What Happens to Ageing, Idle and Discontinued Parts?
Idle stock is an unavoidable but manageable cost with spare parts. In our representative example total stock is ₺14,000,000 and 612 items that have not moved for 24 months hold ₺3,080,000 (22.0%). Of these, 140 items are critical or insurance spares (₺1,470,000) and stay; the remaining 472 items, ₺1,610,000, are disposal candidates. With a 30% buy-back, ₺483,000 comes back in cash and carrying cost falls by ₺402,500 a year. Look at the valuation effect in our inventory valuation article and settle the book entry with your accountant.
A last-time buy is the decision to buy the lifetime need of a part at once when the model goes out of production. The calculation: remaining machine life × number of machines × failure rate. 12 machines, 0.05 failures a year, 8 years: λ = 12 × 0.05 × 8 = 4.8 units. For 95% Poisson requires s = 9 (94.4% at s = 8; 97.5% at s = 9). If machine life stretches to 10 years, λ = 6 and s = 10. Of the 9 units you buy, about 4.2 are left unused on average; that is a deliberate insurance premium. The alternatives are a substitute part or replacing the machine.
Why Are Planned and Unplanned Demand Handled Separately?
Of 1,240 yearly issue lines, 760 (61.3%) come from planned maintenance work orders; that demand is known in advance and is a procurement plan, not a stock decision: you order against the work order date. The remaining 480 lines (38.7%) are unplanned breakdowns, and every calculation in this article is for them. To separate the two, each issue must be linked to a work order type.
Three more rules: the recommended spare parts list is built by comparing the manufacturer's advice in the machine's parts tree with your own failure history (if they conflict, trust your own data); substitute part mapping is defined only after quality approval; an undocumented part is never fitted to a critical machine. For serial tracking, see our traceability article. If you count critical parts 4 times a year, mid-class parts twice and the rest once, you get 280 × 4 + 900 × 2 + 2,320 × 1 = 5,240 count lines; the counting method is detailed in our inventory counting guide.
Which Metrics Do You Track?
| Metric | Calculation | Example |
|---|---|---|
| Part availability (first-request fill) | Filled ÷ unplanned requests | 432 ÷ 480 = 90.0%; critical target at least 99% |
| Downtime caused by waiting for parts | Downtime hours a year | 310 h |
| Stock turnover | Yearly consumption ÷ average stock | ₺4,200,000 ÷ ₺14,000,000 = 0.30 |
| Idle stock share | 24-month idle value ÷ stock | 3,080,000 ÷ 14,000,000 = 22.0% |
| Emergency orders | Count × emergency freight | 46 × ₺3,800 = ₺174,800 |
Low turnover alone is not a bad sign for spare parts; read it together with availability and downtime hours.
How Do You Calculate the Payback?
Suppose analysis, classification, rule set-up and system work for the spare parts regime cost ₺540,000, with ₺90,000 a year for data upkeep. Yearly gains: downtime falls from 310 to 190 hours, 120 h × ₺2,500 = ₺300,000; disposal carrying saving ₺402,500; pooling ₺21,000; emergency orders fall from 46 to 20, 26 × ₺3,800 = ₺98,800. On the negative side, carrying the ₺380,000 of stock added for critical parts costs ₺95,000. Net = 300,000 + 402,500 + 21,000 + 98,800 − 95,000 − 90,000 = ₺637,300 a year. Payback: 540,000 ÷ 637,300 × 12 ≈ 10.2 months.
Sensitivity: if the downtime gain halves (₺150,000 less) net is ₺487,300 and payback about 13.3 months; if it never materialises, net is ₺337,300 and about 19.2 months. If the disposal does not happen, neither does its carrying saving, so commit to the disposal.
How Do You Set Up Spare Parts Inventory Management in Six Steps?
- List the parts: from machine trees, linking item, machine and supplier.
- Assign criticality: impact, whether a backup exists, lead time.
- Classify demand: smooth, erratic, intermittent or lumpy using ADI and CV².
- Set the target and stock level: service level by class; s from the Poisson table; hold, share or fast-supply decision.
- Set up renewal and exit: repair loop, last-time buy, disposal rule.
- Measure: availability, downtime hours, idle share, emergency orders; review quarterly.
Recommended reading: What is field service management software? Technician assignment, van stock and payback guide
Recommended reading: How to manage supplier risk
Spare Parts and Inventory Software With İnovabil
At İnovabil our focus is building software from scratch for your company, and ERP and warehouse solutions are part of it. We built a warehouse management system for Sleepy, logistics and shipment planning for Karyak, purchasing and CRM for Avcılar İnşaat and a purchasing system for İZBAN. We do not have a separate product for a stock with many items and irregular demand such as spare parts; in requirements analysis we put your need in writing with criticality, demand pattern and downtime cost, and choose the right solution together. Our working steps are on our process page, and the ERP side is described in our ERP development service.
Frequently Asked Questions
What is spare parts inventory management?
It is the management of stock for parts with rare, irregular demand and often long lead times, using a service level set by criticality. The aim is to cut downtime caused by stock-outs and unnecessary capital tied up in stock at the same time.
What is intermittent demand?
Demand that is zero in most periods and arrives occasionally, sometimes in lumps. With ADI of 1.32 or more and CV² below 0.49, the common classification calls it intermittent. A classic average misleads on such demand.
How do you choose a service level target?
By the part's criticality. A part that stops the line and has no backup gets a high target such as 99%; an auxiliary part a low one such as 85%. Each step up is compared with the stock value and the expected downtime loss.
Should an expensive spare part be held in stock?
Yes, if the yearly expected downtime gain is larger than the part's yearly carrying cost. If it fails very rarely and can be supplied fast, holding it gains nothing; if it is highly critical, hold it as an insurance spare.
What do you do when a model is discontinued?
Work out the lifetime need from remaining machine life, number of machines and failure rate; then either make a one-off last-time buy by your service level target or compare a substitute part with replacing the machine.