A company has ten projects running at once, but only five teams to run them. Every project is "urgent", every request has an owner, and none of them finishes on time. The problem is rarely the management of a single project. It is that nobody makes a systematic decision about which projects start, which wait and which get stopped. Project portfolio management (PPM) manages exactly that set of decisions.
In this guide we explain the difference between a project, a program and a portfolio, how a request passes through the intake gate, weighted scoring, selecting by capacity, the hidden cost of running too many projects, portfolio balance, shared-resource conflicts, the monthly review rhythm and the decision to stop a project, all with worked examples. Every figure is representative; none is an industry average or data from a specific company.
What Is Project Portfolio Management (PPM)?
Project portfolio management is the practice of selecting, balancing, tracking and, when needed, stopping all the projects a company runs or plans to run, under one roof and with shared criteria. Project management focuses on doing the project right; portfolio management focuses on doing the right projects.
| Concept | Core question | Example | Focus |
|---|---|---|---|
| Project | How, by when and with what budget does this work finish? | Dealer portal v2 | Scope, time, cost |
| Program | How do related projects reach a shared goal? | Dealer portal, ERP connection and training projects | Dependencies, shared benefit |
| Portfolio | Which projects should we select with our capacity, and which should we drop? | This quarter's 5 projects | Priority, balance, capacity, benefit |
We covered how to build the plan for a single project in our project plan guide. This article deals with the layer above it, where those plans compete for the same people. You can also look at our task and project management software service page.
Why Is Running Many Projects at Once Expensive?
Because as the amount of work in progress grows, every item takes longer to finish and people lose time switching context. Both are invisible bills.
Little's law ties average waiting time in a system to throughput: lead time = work in progress (WIP) ÷ items finished per unit of time. Our example team has 10 people, a 13-week quarter and a 20% loss to leave and meetings. Net capacity is 10 × 13 × 0.8 = 104 person-weeks; after setting aside 24 for mandatory work and 8 for urgent items, 72 person-weeks remain for projects. Weekly capacity is 72 ÷ 13 ≈ 5.54 person-weeks; if the average project takes 13.6 person-weeks, about 5.54 ÷ 13.6 ≈ 0.407 projects finish per week.
| Concurrent projects (WIP) | Lead time | Calculation |
|---|---|---|
| 3 | 7.4 weeks | 3 ÷ 0.407 |
| 5 | 12.3 weeks | 5 ÷ 0.407 |
| 10 | 24.6 weeks | 10 ÷ 0.407 |
Each extra concurrent project lengthens average lead time by roughly 2.46 weeks. Context switching comes on top: efficiency falls as the number of projects per person rises. The efficiency rates below are representative; measure your own.
| Projects per person | Efficiency | Effective capacity | Loss (person-weeks) | Cost per quarter |
|---|---|---|---|---|
| 1 | 100% | 72 | 0 | ₺0 |
| 2 | 85% | 61.2 | 10.8 | ₺486,000 |
| 3 | 70% | 50.4 | 21.6 | ₺972,000 |
The cost uses one person-week = 5 days × ₺9,000 = ₺45,000: 10.8 × ₺45,000 = ₺486,000. If you launch ten projects together (two per person), effective capacity drops to 61.2 person-weeks. Ten average-sized projects total 136 person-weeks of effort, and finishing them takes 136 ÷ (61.2 ÷ 13) ≈ 28.9 weeks, which does not fit in the quarter. Five projects need only 68 ÷ 5.54 ≈ 12.3 weeks. For the resource side in detail, see our resource and capacity planning guide.
How Does a Request Pass the Intake Gate?
Every request enters through a single gate and moves through stages before it joins the portfolio; whatever does not pass goes to a "later" list. The gate is not there to block good ideas but to commit capacity only to requests that are ready.
The request form is short, with required fields: problem statement, requester, affected users, target measure, estimated effort range, dependencies and the current workaround. In the example quarter 24 requests arrived; after removing duplicates, vague items and merged ones, 10 candidates remained (14 dropped out). The depth of the gate scales with effort.
| Estimated effort | Required document | Decision maker |
|---|---|---|
| Under 8 person-weeks | Request form; outside the portfolio, goes to the team backlog | Team lead |
| 8–23 person-weeks | One-page short business case | Portfolio board |
| 24 person-weeks and above | Full business case, risks and phases | Portfolio board and management |
The thresholds are representative; adjust them to your own project sizes. We described how a full business case is prepared in our guide to building a business case for a software investment.
How Are Projects Scored?
Weighted scoring puts different kinds of projects side by side on one scale. Each criterion is scored 1–5; score = Σ weight × criterion score. For risk and effort, 5 means "low risk, low effort".
- Strategic fit (35%): Contribution to the company's annual goal.
- Return (30%): Revenue growth, cost reduction or risk reduction.
- Risk (15%): Technical, dependency and uncertainty risk; 5 is lowest risk.
- Effort (20%): Person-weeks required; 5 is lowest effort.
The weights add up to 100% (35 + 30 + 15 + 20). Mandatory work, such as legal, security and contractual obligations, is not scored; it is set aside from capacity up front. The 10 example candidates are below. P2's score: 0.35 × 3 + 0.30 × 5 + 0.15 × 4 + 0.20 × 4 = 1.05 + 1.50 + 0.60 + 0.80 = 3.95.
| Project | Strategic | Return | Risk | Effort | Score | Effort (person-wks) |
|---|---|---|---|---|---|---|
| P2 Invoice reconciliation automation | 3 | 5 | 4 | 4 | 3.95 | 10 |
| P1 Dealer portal v2 | 5 | 4 | 3 | 2 | 3.80 | 20 |
| P3 Warehouse barcode rollout | 4 | 4 | 4 | 3 | 3.80 | 14 |
| P5 Management dashboard | 3 | 3 | 5 | 4 | 3.50 | 8 |
| P9 Supplier portal | 3 | 4 | 3 | 3 | 3.30 | 16 |
| P10 Website refresh | 3 | 2 | 5 | 4 | 3.20 | 9 |
| P4 Customer portal | 4 | 3 | 3 | 2 | 3.15 | 22 |
| P6 Mobile field app | 4 | 4 | 2 | 1 | 3.10 | 30 |
| P7 Legacy report migration | 2 | 2 | 4 | 3 | 2.50 | 12 |
| P8 Ticket classification | 2 | 3 | 2 | 2 | 2.30 | 16 |
P1 and P3 tie; in a tie, the one with higher strategic fit (P1) goes first. Scoring is a decision aid, not a verdict: when the gap between scores is small (for example 3.15 and 3.10), judgment and dependencies decide. For the same logic at feature level, see our guide to RICE prioritization, and for goal setting, our OKR article.
How Do You Select Projects by Capacity?
Go down the score order and make sure total effort does not exceed portfolio capacity; skip a project that does not fit and look at the next one. The rule is not "the top N projects" but "the best set that stays within capacity".
Total demand is 10 + 20 + 14 + 8 + 16 + 9 + 22 + 30 + 12 + 16 = 157 person-weeks; capacity is 72, so demand is 157 ÷ 72 ≈ 2.18 times capacity. Capacity comes out like this:
| Item | Person-weeks | Share |
|---|---|---|
| Gross capacity: 10 people × 13 weeks | 130 | — |
| Leave, meetings and loss (20%) | −26 | — |
| Net capacity | 104 | 100% |
| Mandatory work and maintenance | 24 | 23.1% |
| Urgent-work buffer | 8 | 7.7% |
| Allocated to the portfolio | 72 | 69.2% |
The selection: P2 (10, running total 10), P1 (20, total 30), P3 (14, total 44), P5 (8, total 52), P9 (16, total 68). Adding the next one, P10 (9), would reach 77 and exceed 72; P4, P6, P7 and P8 do not fit either. The selected total is 68 person-weeks (68 ÷ 72 = 94.4%); the remaining 4 person-weeks go to small requests. Being left out does not mean "bad project": P6, the mobile field app, is a good candidate at 3.10, but its 30 person-weeks do not fit this quarter; splitting it into phases and considering the first phase next quarter is possible.
Ranking by score can disadvantage big projects, so look at value per unit of effort too: 3.50 ÷ 8 ≈ 0.44 for P5, 3.80 ÷ 20 = 0.19 for P1. Read both rankings together and discuss the difference at the board.
How Do You Build Portfolio Balance?
Choosing only the highest scores can tilt the portfolio toward one type of work. For balance, split work by type and set a target range for each.
| Type | Selected projects | Person-weeks | Share | Target (representative) |
|---|---|---|---|---|
| Growth | P1, P9 | 36 | 52.9% | 40–60% |
| Efficiency | P2, P3, P5 | 32 | 47.1% | 40–60% |
| Total | 5 projects | 68 | 100% | — |
36 ÷ 68 = 52.9% and 32 ÷ 68 = 47.1%; both sit inside the target range. Other axes are tracked too: the share of risky and innovative work (for example at most 20%), short- versus long-term return, and concentration in a single business unit. None of the five selected projects is high-risk; this is a "safe" quarter, but the innovation share is zero. Choosing that knowingly beats choosing it by accident. For holding risks at portfolio level, see our article on managing software project risks.
How Do You Manage Shared-Resource Conflicts and Dependencies?
The real bottleneck of a portfolio is often not total capacity but demand piling up on a single role or person. Build a week-by-week heat map per role.
In the example there are 2 people in the test role, so weekly capacity is 2 × 0.8 = 1.6 person-weeks. P1 testing needs 0.8 per week in weeks 9–12, P3 needs 0.6 in weeks 9–12 and P9 needs 0.7 in weeks 10–13.
| Week | Demand | Capacity | Load |
|---|---|---|---|
| 9 | 0.8 + 0.6 = 1.4 | 1.6 | 87.5% |
| 10–12 | 0.8 + 0.6 + 0.7 = 2.1 | 1.6 | 131.3% |
| 13 | 0.7 | 1.6 | 43.8% |
In weeks 10–12 demand exceeds capacity by 0.5 per week, 1.5 person-weeks over three weeks. The options: shift a project, find extra testing capacity or reduce scope. If we move P9's testing to weeks 13–15, weeks 10–12 drop to 1.4 ÷ 1.6 = 87.5%; the price is a three-week delay for P9. That decision is deliberate because you saw the conflict in advance. The same goes for dependencies: if one project's output is awaited by another, their schedules are managed together.
How Do You Run a Portfolio Review Meeting?
Monthly, short and data-driven. The goal is not to report progress but to decide: continue, change, postpone or stop.
- Attendees: The portfolio owner, relevant business unit managers and the technical lead; at most six people.
- Agenda: Project health (green, amber, red), capacity and bottleneck roles, new requests, stop candidates.
- Output: One decision and one owner per project, recorded in a decision log.
- Quarterly: Scores and capacity are recalculated and the next quarter's portfolio is selected.
The monthly management effort is small: 90 minutes × 6 people = 9 hours, plus 6 hours of preparation makes 15 hours; at ₺300 per hour that is ₺4,500 a month. For what different tools do in day-to-day work tracking, see our guide on task tracking software.
When Should a Project Be Stopped?
When the remaining cost no longer justifies the remaining benefit. Only the future counts in the decision; effort already spent is a sunk cost and stays out of it.
Example: A project has an approved budget of 20 person-weeks. 12 person-weeks have been spent (12 × ₺45,000 = ₺540,000, sunk). The annual net benefit is ₺720,000, or ₺60,000 a month. Two scenarios:
| Scenario | Remaining effort | Remaining cost | Remaining payback | Decision (18-month threshold) |
|---|---|---|---|---|
| A: estimate 22 person-weeks | 22 | ₺990,000 | 990,000 ÷ 60,000 = 16.5 months | Continue, re-approve |
| B: estimate 40 person-weeks | 40 | ₺1,800,000 | 1,800,000 ÷ 60,000 = 30 months | Stop |
In both scenarios the ₺540,000 already spent is identical and excluded from the decision. In scenario B the 40 freed person-weeks go to a better project in the queue. The 18-month threshold is representative. Written triggers agreed in advance make the call easier:
- Estimated total effort grows more than 50% beyond the original approval.
- The target measure loses its business relevance.
- The sponsor withdraws and nobody replaces them.
- A critical dependency does not materialize.
- Remaining payback exceeds the threshold.
How Do You Track Benefits and Calculate Payback?
A project is not finished when it ships; the portfolio only learns when you measure whether the approved benefit materialized. Three and six months after closure, compare the measure in the business case with the actual. Example: if P2's approved benefit is ₺80,000 a month and the month-six measurement is ₺64,000, realization is 64,000 ÷ 80,000 = 80%.
The investment in the five selected projects is 68 × ₺45,000 = ₺3,060,000. The approved monthly net benefits (representative) are P1 ₺150,000, P2 ₺80,000, P3 ₺90,000, P5 ₺40,000 and P9 ₺70,000, totaling ₺430,000. Payback (after delivery) is 3,060,000 ÷ 430,000 ≈ 7.1 months. If only 70% of the benefit materializes, it drops to ₺301,000 a month and payback stretches to 3,060,000 ÷ 301,000 ≈ 10.2 months. That is why benefit tracking brings the portfolio's math closer to reality.
You can also calculate the payback of the portfolio practice itself. Setup (template, scoring, dashboard) costs 12 person-days × ₺9,000 = ₺108,000; monthly running cost is ₺4,500. In the scenario with two projects per person, context-switching loss is ₺486,000 per quarter, or ₺486,000 ÷ 3 = ₺162,000 a month, and that is what avoiding it is worth; if only half of it is realized, ₺81,000. Net gain is ₺81,000 − ₺4,500 = ₺76,500; payback is 108,000 ÷ 76,500 ≈ 1.4 months. A more conservative test: to pay back in 12 months you need (4,500 + 108,000 ÷ 12) = ₺13,500 a month, which is only 8.3% of ₺162,000. The figures are representative; recalculate with your own loss and capacity data. For project-level cost and profitability tracking, see our guide to tracking project costs and profitability.
What Are Common Portfolio Management Mistakes?
- Ignoring capacity: Starting every high-scoring project delays all of them.
- Forgetting mandatory work: If maintenance and legal work are not set aside up front, they eat the new projects.
- Treating the score as sacred: When score gaps are small, dependencies and judgment decide.
- Never stopping anything: Sunk-cost thinking keeps weak projects alive.
- Not measuring benefit: Shipping is not the same as delivering the benefit.
- Bending the rule for a person: Skipping the gate for a senior request makes the rule meaningless for everyone.
Running Custom Software Projects in Phases and by Priority with İnovabil
At İnovabil our focus is building custom software from scratch for your company. We work with the six recorded steps on our process page: analysis, design, development, testing, release, and maintenance and support. We do not claim to offer portfolio management or a PMO service; however, during requirements analysis we recommend prioritizing multiple requests, splitting large work into phases and starting with a clearly scoped first release.
We have built CRM, purchasing and mobile for Avcılar İnşaat; a purchasing system for İZBAN; logistics and shipment planning plus wholesale order management for Karyak; warehouse management and a complaint and support management system for Sleepy; and shipment planning for Bofigo. If you have several software requests on the table, send us a short summary and we will discuss in writing which one should come first.
We recommend reading: Our software development process: step by step from analysis to release
We recommend reading: Our custom software service
Frequently Asked Questions
What is project portfolio management (PPM) and what is it for?
It is the method of selecting all of a company's projects by shared criteria, balancing them against capacity, tracking them and stopping them when needed. The goal is for the projects that create the most value with limited resources to finish together and on time.
What is the difference between project management and portfolio management?
Project management takes a single project to success in scope, time and cost. Portfolio management decides which projects start, which wait and which are stopped.
How do I prioritize projects?
Score them 1–5 on weighted criteria such as strategic fit, return, risk and effort, rank them and pick the best set that stays within capacity. Set mandatory work aside first, and weigh dependencies too when score gaps are small.
How many projects should run at the same time?
It depends on team size; the basic rule is to cap work in progress. In the example, with a 10-person team, 5 projects finish in about 12.3 weeks on average and 10 projects in 24.6 weeks (28.9 weeks with context-switching loss).
Which project should be stopped?
The one whose remaining cost no longer justifies its remaining benefit. Effort already spent stays out of the decision; written triggers agreed in advance (effort growth, the measure losing relevance, the sponsor withdrawing) make the call straightforward.